Update of the Project



Original Planning Sketch
Jennie Castle


Passive House 
Building Energy Rating 'A'

Water borehole installed
150m Geo-thermal borehole installed as heating source for the underfloor heating
Sub-structure services installed- electrical conduits, sewerage
Structure : foundations, rising walls, sub-floor, external and internal walls, structural steel beams
and Posi-floor joists to main house installed.

Main house ready for the next level up!

Precast slabs for the garage scheduled for 10days time together with 
external precast stairs for the pedestrian entrance and the walled garden




Friday, May 9, 2014

Geo Thermal Borehole

The site has been sculpt to create the base platform for the house and to create access for the Geo-thermal borehole drilling. 

The drilling of the Geo-thermal borehole happened today 
by Tom Fogarty Drilling