Tuesday, May 27, 2014

Rising Blockwork Started

The rising blockwork from the foundation to the top of screed level started


365mm insulated block wall construction


200mm of compacted hardcore


Ground Floor Plan


Monday, May 26, 2014

House pegged out

External corners of the the house have been pegged ready for the rising blockwork.






Original pre-planning submission sketch



The Ground Floor Plan


Thursday, May 22, 2014

Foundations Poured


At 7.30am this morning the pouring of the foundations were started and completed by 12.30.


Saturday, May 17, 2014

Foundation trenches completed!

The house set up was done by Philip Byrne of
Byrne & McCabe Design
Graig-na-managh
Co Kilkenny

Centre points of the wall/foundation were marked out for the digger to 'pull' the foundation trenches.






Friday, May 9, 2014

Geo Thermal Borehole

The site has been sculpt to create the base platform for the house and to create access for the Geo-thermal borehole drilling. 

The drilling of the Geo-thermal borehole happened today 
by Tom Fogarty Drilling




Friday, May 2, 2014

Diggers back on Site!



P. J. O'Shea of Smartbuild has been nominated as the Contractor for the new Passive House.
We welcome back P.J. and his team and we're looking forward to seeing this project
 come out of the ground.... !