Tuesday, May 27, 2014

Rising Blockwork Started

The rising blockwork from the foundation to the top of screed level started


365mm insulated block wall construction


200mm of compacted hardcore


Ground Floor Plan


Monday, May 26, 2014

House pegged out

External corners of the the house have been pegged ready for the rising blockwork.






Original pre-planning submission sketch



The Ground Floor Plan


Thursday, May 22, 2014

Foundations Poured


At 7.30am this morning the pouring of the foundations were started and completed by 12.30.


Saturday, May 17, 2014

Foundation trenches completed!

The house set up was done by Philip Byrne of
Byrne & McCabe Design
Graig-na-managh
Co Kilkenny

Centre points of the wall/foundation were marked out for the digger to 'pull' the foundation trenches.